Concreting of the raft foundation of Tower 1 of Blu Marine started on Friday 3rd December at 14:00 and ended on Saturday 4th December at 18:00. 28 hours of nonstop casting, 3 batching plants of concrete supply, 5 concrete pumps, 40 concrete mixer trucks with 300 Cube tests and 120 slump tests with a total of 3800 m3 concrete and 1,100 tons of reinforcement were used in the entire procedure. Along with 140-men construction crew working day and night on “Europe’s New Riviera.”